Summary
A design and construction project for Stark Industries, which will include a sidewalk around the building with safety rails, a walkway to the parking lot, and a wheelchair accessible ramp from the patio. Thor Construction will oversee the design, construction, and inspection of the project. Costs will be $10,000 and the project will take approximately two months to complete.
Background
The current location of Stark Tower was purchased one year ago with the intention of updating the safety features of the building (previously it was damaged due to alien invasion). The Director and the other managers at the tower have been interviewing construction companies, seeking the right price and an emphasis on safety. They want a beautiful addition to their building that can also serve as an exercise area for their employees.
Objective
The project’s objective is to build an easily accessible walkway to facilitate access to the parking lot, and for employees to use for healthy walks during the work day. Going beyond the city’s basic safety codes is important as the health of employees is the top concern of Stark Industries. Our previous work, which related to similar concerns, gives Thor Construction the unique ability of offering the most modern technology and options with respect to safety. The project should also be beautiful aesthetically, and it should enhance the relaxing atmosphere of Stark Tower.
Process
To build a sidewalk that wraps around the entire Stark Tower, construction will be done in a rubber / cement mixture to prevent accidents. The walkway will incorporate appropriate curving to render it exactly ¼ of a mile in length. The walkway and its rails will be textured to help avoid mishaps. The ramp will also be constructed with a low slope for appropriate wheelchair accessibility.
The design table and construction documents are attached. All plans are subject to city approval.
- Materials - See attached sheet.
- Labor - Three daily dedicated employees on site plus overseer.
- Time Table - Two months.
Budget
- Materials: $3,500
- Labor: $5,500
- Permits: $500
- Inspection: $500
- Total Cost: $10,000
Conclusion
Thor Construction provides thorough sidewalk and building safety rails surrounding the ground floor of Stark Tower for aesthetic and inviting accessibility to and from the building that is fully up to code at an incredibly reasonable rate. Contact immediately to lock in this plan and begin next steps.